INDIANAPOLIS — Get ready for construction on I-465 next week.

According to a release from the Indiana Department of Transportation, roadwork on the northwest quadrant of I-465 will make repairs to areas that were damaged by several harsh winters that included extreme freeze and thaw cycles.

Crews will begin in the northwest corner of I-465 on Monday between 56th Street and U.S. 31. Work will continue through late October.

Here are details of the project:

Segment 1

  • Mid-May to beginning of September
  • I-465 northbound and southbound from 56th Street to 96th Street
  • Work will be done weeknights and Saturdays from 8 p.m. to 6 a.m. in northbound lanes and from 8 p.m. to 7 a.m. in southbound lanes.
  • Crews will be milling and repaving in this area.
  • There will be various lane closures in both directions. At least one lane will be open in each direction, but both northbound and southbound could be affected at the same time.

Segment 2

  • Late July to end of October
  • I-465 eastbound and westbound from 96th Street to U.S. 31
  • Work will be done weeknights and Saturdays from 8 p.m. to 6 a.m. in eastbound lanes and 8 p.m. to 7 a.m. in westbound lanes.
  • Crews will be milling and repaving in this area.
  • There will be various lane closures in both directions. At least one lane will be open in each direction, but both eastbound and westbound lanes could be affected at the same time.