INDIANAPOLIS — Construction season will get underway next week on I-465 on the northeast side.
According to a release from the Indiana Department of Transportation, workers will patch and repave segments of I-465 and I-69 from U.S. 31 down to I-70.
Work is scheduled to begin after Memorial Day and continue through October. The project will be completed in four segments with at least one lane open in each direction.
Here's a look at what to expect and when.
Segment 1: I-465 east and west from White River Bridge to I-69
- End of May to middle of August
- Crews will work on the eastbound inside lanes first
- Work will be completed on nights and weekends
- 8 p.m. to 6 a.m. the next morning
Segment 2: I-465 east and west from U.S. 31 to White River Bridge
- Beginning of June to Middle of August
- Weekend lane closures
- 8 p.m. to 6 a.m. Monday morning
Segment 3: I-69 N/S from I-465 to S.R. 37
- Middle of June to End of July
- Work will be completed on nights and weekends
- 8 p.m. to 6 a.m. the next morning
Segment 4: I-465 E/W from I-69 to I-70
- Beginning of August through October
- Work will be completed on nights and weekends
- 8 p.m. to 6 a.m. the next morning