INDIANAPOLIS — A little over a year since the North Split reconstruction project started, the Indiana Department of Transportation (INDOT) has announced that the project is continuing smoothly.
Beginning on May 15, 2021, the North Split construction has advanced due to the construction crews. The construction crews have:
- Successfully demolished 38 of 51 bridges in need of repair
- Placed 217 of 390 precast concrete beams, with the largest weighing approximately 250,000 pounds
- Reconstructed 4 bridges and 1 ramp, which are currently in use
- Used approximately 34,000 cubic yards of structural concrete
- Moved over 560,000 cubic yards of the 1 million total cubic yards of earthwork
As it advances, the interchange is scheduled to reopen by the end of 2022. Aesthetics and local street work near the interchange will continue in the spring of 2023.
By the end of the reconstruction, INDOT hopes to create a more efficient and compact design that will help get rid of factors that can cause high crash rates and congestion.
Once reconstruction is completed, improvements will include:
- 223 new lighting elements, including 12 high-mast tower lights, 176 underpass and monument lights at bridges, and 33 conventional roadway light structures
- Approximately 12,100 linear feet of new sidewalks/trails
- More than 4,500 trees
- More than 5,000 shrubs
For more information on the reconstruction project, visit their website or text "NORTHSPLIT" to 468311.
-
Indiana tornado drill prepares schools, agencies as severe storms loom
Indiana’s statewide tornado drill on Tuesday morning gave schools and emergency agencies a chance to practice their response.
Revitalization project aims to turn northeast side park into community hub
An $800K revitalization project is hoping to transform Doris Cowherd Park on Indy's northeast side into a community hub for residents across the community.
Indianapolis students bring home free books thanks to community partnership
Students at Washington Irving Neighborhood School filled their backpacks with five free books to take home, thanks to a community partnership aimed at building home libraries.
Indy DPW begins higher effectiveness pothole repair
Indianapolis Department of Public Works crews worked to patch potholes along Arlington Avenue and across the city on Tuesday.