INDIANAPOLIS — A little over a year since the North Split reconstruction project started, the Indiana Department of Transportation (INDOT) has announced that the project is continuing smoothly.
Beginning on May 15, 2021, the North Split construction has advanced due to the construction crews. The construction crews have:
- Successfully demolished 38 of 51 bridges in need of repair
- Placed 217 of 390 precast concrete beams, with the largest weighing approximately 250,000 pounds
- Reconstructed 4 bridges and 1 ramp, which are currently in use
- Used approximately 34,000 cubic yards of structural concrete
- Moved over 560,000 cubic yards of the 1 million total cubic yards of earthwork
As it advances, the interchange is scheduled to reopen by the end of 2022. Aesthetics and local street work near the interchange will continue in the spring of 2023.
By the end of the reconstruction, INDOT hopes to create a more efficient and compact design that will help get rid of factors that can cause high crash rates and congestion.
Once reconstruction is completed, improvements will include:
- 223 new lighting elements, including 12 high-mast tower lights, 176 underpass and monument lights at bridges, and 33 conventional roadway light structures
- Approximately 12,100 linear feet of new sidewalks/trails
- More than 4,500 trees
- More than 5,000 shrubs
For more information on the reconstruction project, visit their website or text "NORTHSPLIT" to 468311.
-
Over 500 gather for community meeting with Indy Action Coalition
Over 500 Indianapolis residents gathered to discuss a new homelessness law and ICE enforcement at a community meeting on Thursday.
Southeast side tenants looking for answers after major flooding in apartment
Residents paid renters' insurance along with their rent each month. So, they thought they were protected. Until property managers told them their renters' insurance went towards the building.
Westfield Police investigating "suspicious" death, victim identified
According to a post on social media, Westfield Police responded to the 3900 block of Westfield Road to assist medics on the report of a person down inside a residence at around 7:24 p.m.
Jones remains focused on being ready to start Week 1 after new deal with Colts
Jones returned to the Indianapolis Colts team complex with a new two-year contract worth up to $100 million and a promising timetable for his return to play — the 2026 regular-season opener.